Six Gas Turbines with 200 MW of Flexible Generation Set to be Installed in Zhambyl Region
Six gas turbines with 200 MW capacity will be installed in Zhambyl Region to enhance energy resilience, with the first unit already dispatched from China.

In the Zhambyl Region, six gas turbines with a total capacity of 200 MW will be installed to enhance the resilience of the energy system. The project, undertaken by the Ministry of Energy, aims to develop flexible generation and establish new generating capacities.
As part of this initiative, work has already begun on constructing flexible generating units in the Zhambyl Region. Recently, the first independently designed G50 (F-class) gas turbine with a capacity of 50 MW was dispatched from China to the region.
The project is being implemented following auction tenders held in 2024 on the JSC 'KOREM' trading platform. 'GES Myrzatai' LLP emerged as the winner for the construction of flexible generating units and entered into a contract with the Chinese company Dongfang Turbine for the supply of three G50 gas turbines with a total capacity of 150 MW.
Read also:
Additionally, another three gas turbines with a total capacity of 60 MW are expected. With the inclusion of supplementary equipment, the overall capacity will reach 200 MW. The turbines are anticipated to be operational by 2027.
This project is aimed at developing flexible generation and strengthening the region's energy supply resilience, reports TUKH24, citing the Ministry of Energy's website.
Photo: gov.kz
1 September 2026
Temporary Road Closure on Tlendieva Avenue in Astana Due to Repairs
Tlendieva Avenue in Astana faces temporary closure for repairs from September 1 to September 10, affecting traffic organization.

A section of Tlendieva Avenue is temporarily closed for repair work. In Astana, construction is underway to lay the top layer of the roadway on N. Tlendieva Avenue from Koksal Street to Maskeu Street, reports ЖКХ24, citing the official website of the Astana city administration.
As a result, from September 1 to September 10 of this year, traffic on this section will be partially closed. Traffic will be organized on one side in both directions.
Read also:
Kazakhstan Completes Repair of 377 km of Heating Networks Ahead of New Heating Season
22 October 2026
Water Supply Issues Solved in Saryozek, Network Modernization Begins in Kogaly, Zhetisu
21 October 2026
Over 2,200 Requests from Astana Residents Submitted via TazaQazBot Since Beginning of the Year
21 October 2026
Drivers and pedestrians are advised to plan their routes in advance and be aware of possible changes in traffic organization. Temporary road signs and indicators will be installed to ensure safety and minimize inconvenience.
Photo: gov.kz