77,000 km of Gas Distribution Networks Prepped for Heating Season

JSC 'QazaqGaz Aimaq' prepares 77,000 km of gas networks for the 2026-2027 heating season with a readiness level of 91%.

77,000 km of Gas Distribution Networks Prepped for Heating Season

The Ministry of Energy is placing special emphasis on preparing the fuel and energy sector for the upcoming 2026–2027 autumn-winter period. Reliable operation of the gas infrastructure is a key factor for stable and uninterrupted energy supply to consumers during winter peak loads.

As part of these efforts, JSC "QazaqGaz Aimaq" continues its comprehensive preparation of the gas system for the upcoming 2026–2027 autumn-winter period. The company is responsible for 77,000 km of gas distribution networks and the facilities and structures located on them. Currently, the overall readiness level stands at 91%.

Throughout the summer, "QazaqGaz Aimaq," in cooperation with JSC "Intergas Central Asia," municipal services, regional housing and utilities management, and major enterprises, is conducting a series of planned activities aimed at ensuring reliable, safe, and uninterrupted gas supply to consumers.

As part of the preparation for the heating season, regulatory and preventive maintenance is being carried out. As of today:

  • Current repair of gas distribution points (GRP) and block gas control points (GRPB) is completed at 92%;
  • Current repair of cabinet-type gas control points (GRPSH) and risers (SRP) – at 93%;
  • Current repair of electrochemical protection means – at 93%;
  • Instrument inspection of gas pipelines – at 96%;
  • Technical maintenance of disconnecting devices – at 84%.

In 2026, QazaqGaz Aimaq is also implementing additional measures aimed at eliminating causes of gas pressure drops and minimizing risks of emergencies in gas distribution networks. A total of 227 such measures are planned, out of which 206, or 91%, have already been completed. Specific actions include:

  • Looping of gas pipelines – 93%;
  • Installation of additional block hydrogen reduction stations (SHGRP) – 90%;
  • Replacement of pressure regulators in SHGRP – 90%;
  • Increasing the diameter of gas pipelines – 89%.

A total of 6,306 production personnel are involved in the preparation of the gas system. The company services 287,360 units of GRP, PGB, and SHGRP.

All works are aimed at ensuring stable, uninterrupted, and safe gas supply for consumers during peak winter loads.

reported by Utilities24 with reference to the Ministry of Energy website.