Almaty Assesses Readiness of Heating Facilities for Winter Season

Almaty Mayor Darkhan Satubaldy inspects heating facilities for winter, focusing on renovations and improvements to ensure reliable heating for residents.

Almaty Assesses Readiness of Heating Facilities for Winter Season

During a field inspection, Almaty Mayor Darkhan Satubaldy reviewed the readiness of key heating facilities in the city for the upcoming winter season. The inspection covered the Southern District Boiler House, the 'Orbita' Boiler House, and a section of heating network reconstruction in the Auezov District.

The first site visited was the Southern District Boiler House located on Khojanov Street. This facility supplies heating to 1,553 sites, including 356 apartment buildings and 16 educational institutions. As part of its renovation, three boilers were replaced, another was rebuilt, and auxiliary equipment was updated. The project aims to increase the boiler house's capacity by 55 Gcal/hour and enhance the reliability of heating services for approximately 200,000 consumers.

Next, Darkhan Satubaldy visited the 'Orbita' Boiler House. The facility, operational since 1973, provides heating to 1,312 sites, including 925 apartment buildings, 39 educational facilities, and 17 healthcare institutions. Repairs were conducted here in 2026.

"The main goal is to ensure stable heating for residents during peak demand periods. Facilities with high wear and tear must undergo phased modernization, and all works should be carried out efficiently and within set deadlines," emphasized Darkhan Satubaldy.

The final stop was a section of heating network reconstruction in the area surrounded by Saina, Momyshuly, Ulugbek, and Abay streets. This heating line has been in use since 1988 and has exceeded its intended lifespan, recording 10 damages in the past three years. Currently, the project's readiness is at 80%, with approximately 120 meters of heating network replaced this year. The reconstruction will enhance heating reliability for 45 apartment buildings, 15 other facilities, and one kindergarten.

A meeting with residents was also held at the site. Citizens raised questions and suggestions regarding urban infrastructure. Following the meeting, relevant services were given pertinent instructions.

Overall, 20.1 km of heating networks are undergoing reconstruction and repair in Almaty in 2026, with 15.8 km already completed.

reports ЖКХ24 citing the Almaty city's Akimat website.