9.7 Million Square Meters of Housing Built in Kazakhstan Over Seven Months
Kazakhstan builds 9.7 million square meters of housing in 7 months, enhancing residential projects and affordability.

Kazakhstan has seen the construction of 9.7 million square meters of housing in just seven months, underscoring the country's commitment to expanding residential building projects and providing affordable housing for its citizens.
Plans for 2026 include the completion of 20.4 million square meters of residential space, equivalent to approximately 188,000 housing units.
From the start of the year through the first seven months, 9.7 million square meters of housing have been completed, translating to 92,300 housing units. Currently, this represents 47.5% of the annual plan.
In parallel with the construction of residential properties, the government is implementing measures to support citizens. This year, there are plans to build and acquire 12,000 apartments as credit housing, with a total budget of 155.5 billion tenge. Additionally, 13,500 apartments are slated for purchase to be leased, amounting to 269 billion tenge.
Read also:
There are also ongoing favorable housing programs. Since the beginning of the year, 5,100 loans have been issued at interest rates of 2–5%, totaling 72.7 billion tenge.
Furthermore, through the "Nauryz" program, 11,500 loans have been issued amounting to 339.2 billion tenge.
Housing construction and support for citizens in housing matters continue across all regions of the country, reports ЖКХ24, referencing information from the Committee for Construction and Housing and Communal Services of the Ministry of Industry and Infrastructure Development of the Republic of Kazakhstan.
Photo: gov.kz
18 August 2026
Akmola Region Prepares for Heating Season
Akmola region prepares for heating season with significant infrastructure upgrades and repairs, ensuring energy security ahead of winter.

Preparations are underway for the heating season in the Akmola region, as discussed at a field meeting in Stepnogorsk chaired by Eldos Ramazanov, First Deputy Akim of Akmola Region. Stepnogorsk was chosen as the meeting site due to its strategic role in ensuring the region's energy security.
During the meeting, participants reviewed the state of the heating supply facilities and the progress of the city's infrastructure preparation for the autumn-winter period. Particular attention was given to the repair of heating networks, the upgrading of boiler equipment, and ensuring energy supply reliability.
A major reconstruction of heating networks continues in Stepnogorsk. Of the planned 8.5 km in the first phase, 7.4 km, or 87%, has been repaired. The work is expected to be completed by mid-September. Simultaneously, the repair of the main heating network is underway, with half of the planned work completed so far.
The upgrade of the Stepnogorsk Combined Heat and Power Plant is also ongoing. Current work involves repairing boilers, turbines, chimneys, and ash pipelines. Repairs on one boiler and one turbine are complete, and two chimneys have been restored. A 7.5 km heating network has been fully installed.
During the trip, the modular boiler houses in Akkol were also inspected. The checks involved both the progress of the work and the readiness of the equipment for the heating season. Two modular boiler installations are under construction in the city—one on Abay Street and the other at "Central." The first is 90% ready, while the second is at 40%, with completion expected in September.
Across the region, preparations for winter are progressing along several fronts. This year, the reconstruction of 38.2 km of heating networks is planned, with 27.6 km already completed, representing 70%. Boiler replacements are also underway: of the 26 planned, 20 have been installed so far.
Read also:
Kazakhstan Completes Repair of 377 km of Heating Networks Ahead of New Heating Season
22 October 2026
Water Supply Issues Solved in Saryozek, Network Modernization Begins in Kogaly, Zhetisu
21 October 2026
Over 2,200 Requests from Astana Residents Submitted via TazaQazBot Since Beginning of the Year
21 October 2026
In Shchuchinsk, work is being done on the reconstruction of heating networks at boiler houses. Specifically, 5 out of 6 km of the heating network at Boiler House No. 20 have been repaired, with completion expected in September. In Kokshetau, reconstruction of heating networks on Saina and Potanina streets is nearing completion, alongside the repair of district boiler house equipment.
In Atbasar, the modernization of heating networks and the central boiler house is underway, while in the Sandyktau district, the construction of a modular boiler house in Balkashino is 80% complete. In Makinsk, eight boilers are being replaced at a modular boiler house, and in Kosshy, the modernization of boiler equipment continues.
Preparation of social infrastructure and residential properties is also a priority. For the heating season, 517 healthcare facilities and 376 out of 406 educational institutions are ready, and 87% of apartment buildings in the region have been prepared.
Efforts to build up fuel reserves for municipal boilers are ongoing. Agreements for coal supply and accumulation are being concluded in districts and cities throughout the region, and securing an adequate supply of fuel oil for energy sources is also being addressed.
An important focus remains the preparation of electrical networks. Energy transmission companies continue to repair networks and substations to reduce wear further.
In the coming weeks, the main focus will be on completing repairs, flushing and pressure testing of heating systems, accumulating normative fuel reserves, and obtaining readiness certificates. All activities are monitored and must be completed within the specified deadlines.
reports ЖКХ24 with reference to the Department of Energy and Housing-Communal Services of Akmola Region.